How Long Landscape Permitting Takes in Idaho and Washington

By Joshua Tripp, Landscape Architect, ASLA · PLACE Landscape Architecture · Last updated: November 2026
How Long Does Landscape Permitting Take in Idaho and Washington?
The honest answer is anywhere from zero days to most of a year, depending on which review track your project lands in. A backyard planting plan usually needs no permit at all. A retaining wall, a grading plan, a commercial site plan, a dock or a shoreline project each runs through a different agency on a different clock. PLACE Landscape Architecture permits landscape work across Spokane County, Kootenai County, Bonner County and the lakes of North Idaho every year, and the single biggest factor in a smooth schedule is knowing which track you are on before design starts.
This guide maps the common review tracks, gives published timelines where agencies publish them, and explains what slows projects down.
The Short Version
Planting, small patios and paths: usually no permit. Check HOA rules.
Grading and retaining walls: about 2 to 5 weeks to first review comments in Spokane-area jurisdictions, plus revision rounds.
Commercial or multifamily site and landscape plans: about 4 to 6 weeks to first comments in Spokane, often longer elsewhere, plus revisions and any SEPA review.
SEPA environmental review (Washington): adds weeks; the comment period alone is at least several weeks once notice is issued.
Docks and lake encroachments (Idaho): often 1 to 4 months, longer if objections lead to a hearing, and federal review may run in parallel on navigable lakes.
Shoreline permits (Washington): often several months for a Substantial Development Permit.
Everything below explains where those numbers come from.
Spokane, Washington
The City of Spokane publishes target review times on its permit timeline page. Time to first review comments is about 4 weeks for residential permits, 4 weeks for commercial short-route projects including grading, and 5 weeks for commercial long-route projects. Revisions are targeted at about 10 days per round. Most projects need at least one revision round, so plan on 6 to 10 weeks for a commercial site permit if your drawings are complete.
For new development over 7,000 square feet, Spokane's landscape certification program requires a landscape plan stamped by a licensed landscape architect and an inspection before the certificate of occupancy.
Spokane County, Washington
Spokane County's permit processing guide (BP-08) lists goal times, which the county notes are not guaranteed: grading permits in about 10 to 21 business days and new commercial buildings in about 21 business days, with commercial revisions in 5 to 10 business days. Projects that need SEPA review take longer.
Spokane Valley and Liberty Lake run their own permit centers. See our Spokane Valley and Liberty Lake page.
SEPA Review in Washington
Washington's State Environmental Policy Act applies to many commercial, multifamily and public projects. It adds an environmental checklist, a threshold determination and public comment. Spokane County notes SEPA notice requires at least a three-week comment period. The rules in Ecology's SEPA program allow time limits to be extended, so plan conservatively.
Washington Shorelines
Work within shoreline jurisdiction, such as along the Spokane River or a lake, may need a Shoreline Substantial Development Permit, a conditional use permit or an exemption letter. The local government issues the permit, as the state's permit handbook explains, and conditional uses go to the Department of Ecology for final approval. Construction generally must begin within two years of approval. Shoreline permits commonly take several months because of notice, comment and appeal periods.
Kootenai County, Idaho
Kootenai County does not publish a landscape-specific timeline. In 2024, the Coeur d'Alene Press reported county plan reviews running about three months against a target of roughly three weeks because of staffing shortages. Conditions change, so ask the county for current review times when you apply. Cities such as Coeur d'Alene and Post Falls run their own permit departments.
Bonner County and Sandpoint, Idaho
Bonner County regulates land use above the high-water mark, including shoreline setbacks and wetland buffers. Many lakefront projects also need state and federal permits. Our Sandpoint lakefront permitting guide walks through the three agencies that touch a Lake Pend Oreille shoreline and the order to approach them.
Idaho Lakes: Docks and Encroachments
Docks, pilings, boat lifts and shoreline stabilization below the ordinary high-water mark need an encroachment permit from the Idaho Department of Lands. Under IDAPA 20.03.04.030, notice must be published within 10 days of a complete application, objections are due within 30 days of first publication, and if a hearing is held it must happen within 90 days of acceptance. IDL's single-family dock handout lists a $425 application fee. On Lake Pend Oreille, the U.S. Army Corps of Engineers may also need to authorize the work.
What Slows Permits Down
Incomplete submittals. The review clock often doesn't start until the application is complete.
Designing before checking constraints. A wetland or shoreline buffer discovered after design means redrawing and resubmitting.
Too many revision rounds. Clear, coordinated drawings usually clear in one or two rounds.
Staffing and seasonal backlogs. Spring submittals compete with every other project in the county.
Parallel agencies. Lakefront work can involve a county, a state agency and a federal agency. Start all of them early.
How PLACE Handles Permitting
We research the permit path during site analysis, before concept design, so the plan is drawn inside the rules instead of fixed after review. We prepare and stamp landscape plans, coordinate with civil engineers and surveyors, and respond to review comments. Permitting effort is part of why some projects cost more to design; our pricing guide explains how. For multifamily and mixed-use work, see our housing and mixed-use landscape design page.
Frequently Asked Questions
How long does a landscape permit take in Spokane?
About 4 to 5 weeks to first review comments for most residential and commercial permits, with about 10 days per revision round, according to the City of Spokane's published targets.
Do I need a permit to landscape my yard in Idaho or Washington?
Usually not for planting and small hardscape. Grading, tall retaining walls, pools, structures and work near water usually need permits.
How long does a dock permit take in Idaho?
Often one to four months for a clean single-family application, longer if objections trigger a hearing or federal review is needed.
What is SEPA and will my project need it?
SEPA is Washington's environmental review law. Many commercial, multifamily and public projects need it; most single-family landscapes don't.
Why is Kootenai County permitting slow?
The county reported staffing shortages in 2024 that stretched plan review to about three months. Ask for current times when you apply.
Can a landscape architect speed up permitting?
A landscape architect can't change agency timelines, but complete, coordinated drawings and early constraint research reduce revision rounds. Contact PLACE to talk through your project's permit path.